In August 2017, Water. Desalination + reuse (Faversham House) reported, citing Voice of San Diego, that the Carlsbad desalination plant had delivered almost a fifth less water than the San Diego County Water Authority ordered in the year to the end of June 2017. Output reached 40,400 acre-feet (about 50 million m³) against 49,600 ordered. Production stopped on 46 days, including 15 days due to an algal bloom in April and 10 days for tank repairs in February. Operator Poseidon paid $3.5 million in penalties.
The report showed how strongly a large seawater desalination plant depended on algal conditions and maintenance, and that supply contracts with fixed ordered volumes passed outages on to the operator financially.