In September 2017, Water. Desalination + reuse (Faversham House) reported that the Santa Ana Regional Water Quality Control Board had accepted as complete Poseidon's application for the proposed Huntington Beach seawater desalination plant. Poseidon sought renewal and amendment of its ocean discharge permit and a finding that the plant met California's desalination rules of May 2015. To that end the developer had redesigned intake and discharge and filed 100 reports and technical memos. A detailed review was next, followed later by a draft permit for public comment.
The report showed how long the permitting path for large seawater desalination in California was under the 2015 rules: a complete application merely opened the actual review.