  • Philippines, 2017: Mactan Rock Industries to expand desalination

    Philippines, 2017: Mactan Rock Industries to expand desalination

    In June 2017, Water. Desalination + reuse (Faversham House), citing the Manila Bulletin, reported that Mactan Rock Industries had obtained a loan of PHP 500 million (about USD 10 million) granted by Development Bank of the Philippines. The money was to raise desalination output at Mactan Economic Zones 1 and 2 and at the Mactan-Cebu International Airport fivefold, to 25,000 m³/day from 5,000. The company ranked among the country's biggest desalination suppliers and ran a 22,000 m³/day seawater plant in Cebu City plus several smaller brackish and seawater units.

    The report showed rising demand from industry and tourism in the Philippines prompting private desalination operators to expand with the help of bank loans.

    Source: Water. Desalination + reuse (Faversham House)

  • North Carolina, 2017: Delay for H2GO desalination plant

    North Carolina, 2017: Delay for H2GO desalination plant

    In June 2017, Water. Desalination + reuse (Faversham House) reported, citing broadcaster WECT, that county commissioners in Brunswick County backed a pause to H2GO's planned reverse osmosis plant on 5 June 2017. The facility was to deliver 15,000 m³/day (4 MGD) at a cost of about USD 30 million. In May 2017 it had received an NPDES discharge permit, and two of five construction contracts worth USD 3.4 million had been let. A petition by 900 residents had sought a delay until after the utility's board vote in November 2017.

    The report showed that even permitted and partly contracted desalination projects in the US could hinge on local elections and resident opposition.

    Source: Water. Desalination + reuse (Faversham House)

  • Chennai, 2017: Desalination supplies 40 percent of city water

    Chennai, 2017: Desalination supplies 40 percent of city water

    In June 2017, The Times of India reported that Chennai was drawing around 40 percent of its piped water from the sea during the state's most severe drought in 142 years. The Minjur and Nemmeli plants, each rated at 100,000 m³/day, delivered roughly 180,000 of the 470,000 m³/day distributed by the utility CMWSSB, against demand of 1.3 to 1.4 million m³/day. CMWSSB paid 60 rupees per cubic metre for Minjur water and about 30 for Nemmeli. Two more plants were proposed at Perur.

    The report showed how a monsoon-dependent city came to rely on seawater during a crisis, even though experts regarded desalination there as a costly last resort.

    Source: The Times of India

  • Jordan, 2017: First seawater desalination plant starts up in Aqaba

    Jordan, 2017: First seawater desalination plant starts up in Aqaba

    In June 2017, Water. Desalination + reuse (Faversham House) reported that Jordan's first seawater reverse osmosis facility, on the Gulf of Aqaba, had started producing water in April 2017. Local firm AquaTreat handled engineering, construction and technology for the 15,000 m³/day unit, which combined microfiltration, ultrafiltration and reverse osmosis. Aqaba Water Company took 70 per cent of the output and fertiliser maker KEMAPCO 30 per cent. Cooling water discharged by KEMAPCO fed the plant, and brine went back into its drain. A seven-year BOT arrangement applied.

    The report showed Jordan entering seawater desalination through a small industrial-scale plant, while the far larger Red Sea-Dead Sea scheme of 220,000 m³/day remained at the planning stage.

    Source: Water. Desalination + reuse (Faversham House)

  • Oman, 2017: OPWP expects shift to reverse osmosis

    Oman, 2017: OPWP expects shift to reverse osmosis

    In May 2017, Water. Desalination + reuse (Faversham House) reported that Oman Power and Water Procurement Company (OPWP) had released its power and desalinated water outlook to 2023. In the main MIS grid, water demand was set to climb by 5 % annually to 1.1 million m³/day, and in Dhofar 9 % to 231,000 m³/day. Bidders for Salalah and Barka II had chosen reverse osmosis over multi-stage flash without being asked. New capacity included Qurayyat (200,000 m³/day, 2017) and Barka IV (281,000 m³/day, 2018).

    The report showed power-water co-location losing weight in Oman, with the procurer expecting future bids to favour reverse osmosis on cost grounds.

    Source: Water. Desalination + reuse (Faversham House)

  • Mexico, 2017: US permit clears Rosarito cross-border pipeline

    Mexico, 2017: US permit clears Rosarito cross-border pipeline

    In May 2017, Water. Desalination + reuse (Faversham House) reported that Otay Water District in California had obtained a US presidential permit for a pipeline crossing the border into Mexico. This removed a key obstacle for the Rosarito Beach desalination project planned by Consolidated Water in Baja California. The plant was to supply 379,000 m³/day, of which 10 to 20 percent was earmarked for Otay. In March 2017, project company Aguas de Rosarito had sought a higher tariff than its original contract with the state, citing changed economic conditions.

    The report showed that cross-border water supply needed approval at the highest state level as well as technology and finance, and that southern California saw desalination as a drought-proof source.

    Source: Water. Desalination + reuse (Faversham House)

  • Chile, 2017: Nine consortia compete for Atacama desalination

    Chile, 2017: Nine consortia compete for Atacama desalination

    In May 2017, Water. Desalination + reuse (Faversham House), citing Diario Financiero, reported that nine consortia were competing for a seawater desalination plant in Chile's Atacama region. State utility Econssa had launched the tender in March 2017. The reverse osmosis plant was to grow in three phases (39,000, 39,000 and 26,000 m³/day) to 104,000 m³/day for Copiapó, Caldera, Chañaral and Tierra Amarilla. Estimated cost was 250 million US dollars, 100 million for phase one. Bids were due in August, with an award expected late in 2017.

    The report showed lively competition for a state desalination project in Chile. Phased expansion tied the investment to the growing demand of the towns served.

    Source: Water. Desalination + reuse (Faversham House)

  • South Africa, 2017: Koeberg nuclear plant to add desalination unit

    South Africa, 2017: Koeberg nuclear plant to add desalination unit

    In May 2017, Water. Desalination + reuse (Faversham House), citing News24, reported that utility Eskom planned a desalination unit to supply its own Koeberg nuclear power station. A simple mobile unit was to come first, possibly followed by a larger integrated system. The step followed Cape Town's water shortage: level 3 restrictions had applied since 1 February 2017, and level 4, capping household use at 100 litres per head daily, was proposed from 1 June. Eskom also offered a site for a municipal unit of 2,500 to 5,000 m³/day.

    The report showed how Cape Town's 2017 drought prompted quick desalination measures, first for large users such as power stations and as a precursor to a bigger municipal plant.

    Source: Water. Desalination + reuse (Faversham House)

  • Victoria, 2017: Minimum 15 GL order from the desalination plant

    Victoria, 2017: Minimum 15 GL order from the desalination plant

    In May 2017, the Victorian Government ordered 15 gigalitres of water (15 million m³) from the Victorian Desalination Plant for 2017/18, the set minimum amount. The order followed advice from Melbourne Water in consultation with the three metropolitan water retailers. Water Minister Lisa Neville said no one's water bills would rise because of it. The orders were funded from the sale of surplus Renewable Energy Certificates. In May 2017, Melbourne's storages were 105 GL lower than in May 2015.

    The report showed a desalination plant used as a precaution to stabilise storage levels rather than only in a crisis. Funding through unused energy certificates kept the cost away from households.

    Source: Utility Magazine

  • Saudi Arabia, 2017: Sepco III to complete Yanbu phase three

    Saudi Arabia, 2017: Sepco III to complete Yanbu phase three

    In May 2017, Water. Desalination + reuse (Faversham House), citing Reuters, reported that the Saudi Saline Water Conversion Corporation (SWCC) had brought in China's Sepco III Electric Power and Construction Corp to finish phase three of the Yanbu power and water scheme. Works had been suspended since January after a dispute between SWCC and Samsung Engineering over changes to the scheme. Around 60 per cent of construction was complete. The complex was planned to deliver 550,000 m³/day of drinking water and 2,500 MW of power, using GE Water technology.

    The report showed that even large SWCC projects could change main contractor midway through construction, with a Chinese builder stepping in to take over completion.

    Source: Water. Desalination + reuse (Faversham House)